Lockheed Martin Corp. (LMT) won the F-35 Joint Strike Fighter program in the wake of the Sept. 11, 2001, attacks when U.S. B-52 bombers were pummeling the Taliban and Pentagon spending was unleashed.
Ten years and $66 billion later, the aircraft is still in development, five years behind schedule and 64 percent over cost estimates. The Obama administration may cancel some models and also cut the Pentagon’s orders.
The plane, envisioned as the affordable stealth fighter for the U.S. and allies, has turned into a budget target.
“I’d blame the program’s setbacks on the fact that we lived in a rich man’s world,” said Jacques Gansler, a former Pentagon chief weapons buyer in the Clinton administration and now a professor at the University of Maryland at College Park. “There has been less emphasis on cost over the past 10 years,” he said.
During that decade, the F-35 cost rose along with the Pentagon’s overall budget for developing and buying new weapons, which increased 62 percent to $208 billion in 2011 from $128 billion in 2001. The jet has been bedeviled by a costly redesign, faulty cost estimates, fluctuating order quantities, and infrastructure built on assumptions of rapid production.
Even so, the plane has not failed or faced crippling technical problems in flight tests, and Lockheed says the jets are meeting test goals. Last month, the Marine Corps version, the most complex variant, demonstrated the first short takeoff and vertical landing on a ship.
Variants
Still, Army General Martin Dempsey, chairman of the Joint Chiefs of Staff, said last month the U.S. may not be able to afford three variants, for the Air Force, Navy aircraft carriers, and the Marine Corps.
Former Defense Secretary Donald Rumsfeld hailed the F-35 as a transformational family of airplanes for the U.S. and its allies in three variants built off a common chassis and assembly line. The jet would be the “world’s premier strike platform beginning in 2008,” said Pete Aldridge, the then-top U.S. weapons buyer, said in October 2001, at a Pentagon news conference.
Yet the program has been delayed by five years, and development costs have grown 64 percent to $56.4 billion since the program’s inception, according to data from the U.S. Government Accountability Office. The overall cost, including procurement of about 2,400 U.S. aircraft, has risen to $382.5 billion, according to an independent estimate by the congressionally mandated Cost Assessment and Program Evaluation office.